Project Start Date: Sun 3/1/09
Project Finish Date: Sun 9/6/09
ID | Percent_Complete | Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
---|---|---|---|---|---|---|---|
1 | 100% | RV reservation | 0 days | Sat 3/28/09 | Sat 3/28/09 | JB | |
2 | 100% | Truck reservation | 2 days | Mon 6/1/09 | Tue 6/2/09 | JB | |
3 | |||||||
4 | 100% | Camp Meeting | 1 day | Fri 4/17/09 | Fri 4/17/09 | Team | |
5 | |||||||
6 | 100% | Theme camp questionnaire | 92 days | Wed 4/1/09 | Wed 7/1/09 | Dale | |
7 | 100% | Determine what real estate we want | 0 hrs | Wed 4/1/09 | Wed 4/1/09 | Team | |
8 | 100% | Brainstorm interactivity | 0 hrs | Fri 4/17/09 | Fri 4/17/09 | 4 | Team |
9 | 100% | Brainstorm camp features | 0 hrs | Fri 4/17/09 | Fri 4/17/09 | 4 | Team |
10 | 100% | Finalize interactivity | 5 days | Mon 4/27/09 | Fri 5/1/09 | 8FS+2 wks | Team |
11 | 100% | Finalize camp features | 1 day | Mon 4/27/09 | Mon 4/27/09 | 9FS+2 wks | Team |
12 | 100% | Theme Camp Layout | 5 days | Sat 5/2/09 | Wed 5/6/09 | 7,11,10 | Team |
13 | 100% | Create theme camp map | 1 day | Sun 5/3/09 | Sun 5/3/09 | 12 | JB |
14 | 100% | Publish theme camp layout web page | 32 hrs | Sun 5/3/09 | Wed 5/6/09 | 13 | Dale |
15 | 100% | Submit theme camp questionnaire | 3 wks | Thu 5/7/09 | Thu 5/21/09 | 14 | Dale,Dawn |
16 | 100% | Submit early arrival list | 1 day | Wed 7/1/09 | Wed 7/1/09 | Dale | |
17 | |||||||
18 | 100% | Luminous Passage | 113 days | Sat 4/11/09 | Sat 8/1/09 | ||
19 | 100% | Design/Build | 112 days | Sat 4/11/09 | Fri 7/31/09 | ||
20 | 100% | Lamps 1 and 2 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
21 | 100% | Lamps 3 and 4 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
22 | 100% | Lamps 5 and 6 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
23 | 100% | Lamps 7 and 8 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
24 | 100% | Lamps 9 and 10 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
25 | 100% | Lamps 11 and 12 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
26 | 100% | Lamps 13 and 14 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
27 | 100% | Lamps 15 and 16 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
28 | 100% | Lamps 17 and 18 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
29 | 100% | Lamps 19 and 20 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
30 | 100% | Lamps 21 and 22 | 60 days | Sat 4/11/09 | Tue 6/9/09 | Team | |
31 | 100% | 10 Cardboard Benches | 90 days | Fri 4/17/09 | Wed 7/15/09 | JB | |
32 | 100% | Create stencils | 2 wks | Fri 7/17/09 | Sun 7/26/09 | 31 | JB |
33 | 100% | Paint benches | 1 wk | Mon 7/27/09 | Fri 7/31/09 | 32 | Team |
34 | 100% | Cut thirty (30) 2x4s as support stems | 60 days | Sun 4/26/09 | Wed 6/24/09 | Team | |
35 | 100% | Finalize the LP display | 1 day | Sat 8/1/09 | Sat 8/1/09 | 19 | Team |
36 | 62% | Camp Features | 140 days? | Wed 4/1/09 | Tue 8/18/09 | ||
37 | 0% | Croquet | 120 days | Fri 4/17/09 | Fri 8/14/09 | Henry,Monetta | |
38 | 79% | Shade Rooms | 100 days | Sat 4/18/09 | Sun 7/26/09 | ||
39 | 66% | Common Elements | 100 days | Sat 4/18/09 | Sun 7/26/09 | ||
40 | 100% | Lit pillars (for 3 Shade Rooms, 20 pillars) | 66 days | Sat 4/18/09 | Mon 6/22/09 | ||
41 | 100% | Purchase corrugated plastic | 12 wks | Sat 4/18/09 | Tue 6/16/09 | 4 | JB |
42 | 100% | Purchase lighting | 1 day | Wed 6/17/09 | Wed 6/17/09 | 41 | Team |
43 | 100% | Build | 31 days | Sat 5/23/09 | Mon 6/22/09 | Team | |
44 | 100% | 12 Octagonal pillars | 1 wk | Thu 6/18/09 | Mon 6/22/09 | 42 | JB |
45 | 100% | 8 Hexagonal pillars | 1 wk | Sat 5/23/09 | Wed 5/27/09 | JB | |
46 | 100% | 6-sided Shade Room Construction (Make 2) | 44.5 days | Sat 4/18/09 | Mon 6/1/09 | ||
47 | 100% | Design | 30 days | Sat 4/18/09 | Sun 5/17/09 | 4 | Bill,Gary |
48 | 100% | Create construction plan | 1 wk | Mon 5/18/09 | Fri 5/22/09 | 47 | Bill,Gary |
49 | 100% | Hardware spec sheet | 0.5 wks | Sat 5/23/09 | Mon 5/25/09 | 48 | Bill,Gary |
50 | 100% | Purchase hardware | 2 days | Mon 5/25/09 | Wed 5/27/09 | 49 | Team |
51 | 100% | Cut posts (12) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 50 | Bill,Gary |
52 | 100% | Cut beams (12) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 50 | Bill,Gary |
53 | 100% | Cut lentils (12) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 50 | Bill,Gary |
54 | 100% | Make hubs (2) | 3 days | Wed 5/27/09 | Sat 5/30/09 | 50 | Bill,Gary |
55 | 100% | Make roof panels (12) | 5 days | Wed 5/27/09 | Mon 6/1/09 | 50 | JB |
56 | 100% | 8-sided Shade Room Construction (Make 1) | 44.5 days | Sat 4/18/09 | Mon 6/1/09 | ||
57 | 100% | Design | 30 days | Sat 4/18/09 | Sun 5/17/09 | 4 | Bill,Gary |
58 | 100% | Create construction plan | 1 wk | Mon 5/18/09 | Fri 5/22/09 | 57 | Bill,Gary |
59 | 100% | Hardware spec sheet | 0.5 wks | Sat 5/23/09 | Mon 5/25/09 | 58 | Bill,Gary |
60 | 100% | Purchase hardware | 2 days | Mon 5/25/09 | Wed 5/27/09 | 59 | Team |
61 | 100% | Cut posts (7) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 60 | Bill,Gary |
62 | 100% | Cut beams (7) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 60 | Bill,Gary |
63 | 100% | Cut lentils (7) | 2 days | Wed 5/27/09 | Fri 5/29/09 | 60 | Bill,Gary |
64 | 100% | Make hubs (1) | 3 days | Wed 5/27/09 | Sat 5/30/09 | 60 | Bill,Gary |
65 | 100% | Make roof panels (8) | 5 days | Wed 5/27/09 | Mon 6/1/09 | 60 | JB |
66 | 100% | Purchase plastic stripping for curtains | 1 hr | Mon 5/25/09 | Mon 5/25/09 | 49,59 | Dale |
67 | 100% | Octomon | 6 days | Mon 6/1/09 | Sat 6/6/09 | ||
68 | 100% | Purchase new cover and skirt material | 1 day | Mon 6/1/09 | Mon 6/1/09 | Dale | |
69 | 100% | Sew new cover | 1 wk | Tue 6/2/09 | Sat 6/6/09 | 68 | Dale |
70 | 100% | Sew new octomon skirt | 1 wk | Tue 6/2/09 | Sat 6/6/09 | 68 | Dale |
71 | 0% | Critters | 100 days | Sat 4/18/09 | Sun 7/26/09 | ||
72 | 0% | Design | 3 mons | Sat 4/18/09 | Tue 6/16/09 | Dawn | |
73 | 0% | Build | 2 mons | Wed 6/17/09 | Sun 7/26/09 | 72 | Team |
74 | 100% | Pillows | 3 days | Mon 6/1/09 | Wed 6/3/09 | ||
75 | 100% | Determine whether new pillows are needed | 2 days | Mon 6/1/09 | Tue 6/2/09 | Dale | |
76 | 100% | If necessary, make new pillows | 1 day | Wed 6/3/09 | Wed 6/3/09 | ||
77 | 100% | Buy fabric | 1 day | Wed 6/3/09 | Wed 6/3/09 | 75 | Dale |
78 | 100% | Shade Room 1: Rose | 32 days | Sat 4/18/09 | Tue 5/19/09 | ||
79 | 100% | Design | 32 days | Sat 4/18/09 | Tue 5/19/09 | ||
80 | 100% | Curtains | 19 days | Fri 5/1/09 | Tue 5/19/09 | ||
81 | 100% | Locate last year's white curtains | 2 days | Fri 5/1/09 | Sat 5/2/09 | Dale | |
82 | 100% | Measure for curtains/drapes | 1 day | Fri 5/8/09 | Fri 5/8/09 | ||
83 | 100% | Purchase new drape fabric (red) | 1 day | Sat 5/9/09 | Sat 5/9/09 | 82 | Dale |
84 | 100% | Sew new red drapes | 2 wks | Sun 5/10/09 | Tue 5/19/09 | 83 | Ashley |
85 | 100% | Lighting | 26 days | Sat 4/18/09 | Wed 5/13/09 | ||
86 | 100% | Design lighting | 3 wks | Sat 4/18/09 | Sat 5/2/09 | 4 | Team |
87 | 100% | Purchase lighting (if necessary) | 1 day | Sun 5/3/09 | Sun 5/3/09 | 86 | Team |
88 | 100% | Construct lighting (if necessary) | 2 wks | Mon 5/4/09 | Wed 5/13/09 | 87 | Team |
89 | 100% | Shade Room 2: Sunflower | 42 days | Sat 4/18/09 | Fri 5/29/09 | ||
90 | 100% | Design | 42 days | Sat 4/18/09 | Fri 5/29/09 | ||
91 | 100% | Curtains | 42 days | Sat 4/18/09 | Fri 5/29/09 | ||
92 | 100% | Purchase new curtain fabric (white) | 1 day | Sat 5/9/09 | Sat 5/9/09 | 4,82 | Dale |
93 | 100% | Locate last year's yellow drapes | 2 days | Sat 4/18/09 | Sun 4/19/09 | 4 | Dale |
94 | 100% | Sew new white curtains | 2 wks | Wed 5/20/09 | Fri 5/29/09 | 92,84 | Monetta |
95 | 100% | Seating | 37 days | Sat 4/18/09 | Sun 5/24/09 | ||
96 | 100% | Determine seating | 2 wks | Sat 4/18/09 | Mon 4/27/09 | 4 | Team |
97 | 100% | Purchase materials (if necessary) | 1 day | Tue 4/28/09 | Tue 4/28/09 | 96 | Team |
98 | 100% | Build 5 benches | 2 wks | Wed 4/29/09 | Fri 5/8/09 | 97 | Team |
99 | 100% | Purchase yellow seat fabric | 1 day | Sat 5/9/09 | Sat 5/9/09 | Dale | |
100 | 100% | Sew seat covers | 3 wks | Sun 5/10/09 | Sun 5/24/09 | 99 | Dale |
101 | 100% | Lighting | 26 days | Sat 4/18/09 | Wed 5/13/09 | ||
102 | 100% | Design lighting | 3 wks | Sat 4/18/09 | Sat 5/2/09 | 4 | Team |
103 | 100% | Purchase lighting (if necessary) | 1 day | Sun 5/3/09 | Sun 5/3/09 | 102 | Team |
104 | 100% | Construct lighting (if necessary) | 2 wks | Mon 5/4/09 | Wed 5/13/09 | 103 | Team |
105 | 100% | Shade Room 3: Greenhouse | 35 days | Sat 4/18/09 | Fri 5/22/09 | ||
106 | 100% | Design | 35 days | Sat 4/18/09 | Fri 5/22/09 | ||
107 | 100% | Curtains | 32 days | Sat 4/18/09 | Tue 5/19/09 | ||
108 | 100% | Purchase new curtain material (white) | 1 day | Sat 5/9/09 | Sat 5/9/09 | 4,82 | Dale |
109 | 100% | Locate Sagrada green drapes | 1 day | Sat 4/18/09 | Sat 4/18/09 | 4 | Dale |
110 | 100% | Sew new white curtains | 2 wks | Sun 5/10/09 | Tue 5/19/09 | 108,82 | Monetta |
111 | 100% | Seating | 10 days | Sat 4/18/09 | Mon 4/27/09 | ||
112 | 100% | Determine seating | 2 wks | Sat 4/18/09 | Mon 4/27/09 | 4 | Team |
113 | 100% | Lighting | 35 days | Sat 4/18/09 | Fri 5/22/09 | ||
114 | 100% | Design lighting | 3 wks | Sat 4/18/09 | Sat 5/2/09 | 4 | Team |
115 | 100% | Dawn's Chandelier | 1 mon | Sun 5/3/09 | Fri 5/22/09 | 114 | Team |
116 | 100% | Consolidate drapes and curtains, plastic stripping; Pack | 1 day | Mon 7/20/09 | Mon 7/20/09 | 80,91,107 | Dale |
117 | 100% | Consolidate pillows, covers, octomon cover and skirt; Pack | 1 day | Mon 7/20/09 | Mon 7/20/09 | 74,67 | Dale |
118 | 100% | LED Flower Garden | 105 days | Wed 4/1/09 | Tue 7/14/09 | ||
119 | 100% | Design | 0 days | Wed 4/1/09 | Wed 4/1/09 | Dale | |
120 | 100% | Purchase LEDs, transformers, controllers, wiring | 1 wk | Sat 4/11/09 | Wed 4/15/09 | 119 | Dale |
121 | 100% | Purchase test fabric | 1 day | Sat 4/18/09 | Sat 4/18/09 | 120 | Dale |
122 | 100% | Purchase skeleton wire | 1 wk | Sun 4/19/09 | Thu 4/23/09 | 121 | Dale |
123 | 100% | Test build | 3 days | Fri 4/24/09 | Sun 4/26/09 | 122 | Dale |
124 | 100% | Purchase white fabric | 2 wks | Mon 4/27/09 | Wed 5/6/09 | 123 | Dale |
125 | 100% | Troubleshoot | 1 wk | Thu 5/7/09 | Mon 5/11/09 | 124 | Dale |
126 | 100% | Build flowers | 3 wks | Tue 5/12/09 | Tue 5/26/09 | 125 | Dale |
127 | 100% | build bases | 2 wks | Sun 7/5/09 | Tue 7/14/09 | 126 | Dale |
128 | |||||||
129 | 100% | Garden Gate | 105 days | Sat 4/18/09 | Fri 7/31/09 | ||
130 | 100% | Design | 3 mons | Sat 4/18/09 | Tue 6/16/09 | JB | |
131 | 100% | Purchase materials | 1 wk | Wed 6/17/09 | Sun 6/21/09 | 130 | JB |
132 | 100% | Build | 2 mons | Mon 6/22/09 | Fri 7/31/09 | 131 | JB |
133 | 100% | Lighting | 1 wk | Mon 6/22/09 | Fri 6/26/09 | 131 | JB |
134 | |||||||
135 | 100% | Fencing | 31 days | Sun 4/12/09 | Tue 5/12/09 | ||
136 | 100% | Design | 1 day | Sun 4/12/09 | Sun 4/12/09 | JB | |
137 | 100% | Purchase hardware | 2 wks | Mon 4/13/09 | Wed 4/22/09 | 136 | Team |
138 | 100% | Build | 1 mon | Thu 4/23/09 | Tue 5/12/09 | 137 | Team |
139 | |||||||
140 | 100% | Truck Cover | 50 days | Tue 6/2/09 | Wed 7/22/09 | ||
141 | 100% | Get dimensions | 0 days | Tue 6/2/09 | Tue 6/2/09 | 2 | JB |
142 | 100% | Design cover | 6 wks | Wed 6/3/09 | Thu 7/2/09 | 141 | JB |
143 | 100% | Order cover | 10 days | Fri 7/3/09 | Sun 7/12/09 | 142 | JB |
144 | 100% | Receive cover | 0 days | Wed 7/22/09 | Wed 7/22/09 | 143FS+2 wks | JB |
145 | |||||||
146 | 100% | Truck Steps | 30 days | Wed 7/1/09 | Thu 7/30/09 | ||
147 | 100% | Design | 0 days | Wed 7/1/09 | Wed 7/1/09 | 4 | Gary |
148 | 100% | Build (if necessary) | 6 wks | Wed 7/1/09 | Thu 7/30/09 | 147 | Gary |
149 | |||||||
150 | 38% | Kitchen | 79 days | Mon 6/1/09 | Tue 8/18/09 | ||
151 | 0% | Determine what is needed | 1 wk | Wed 7/1/09 | Sun 7/5/09 | Dawn,Henry | |
152 | 100% | Ground cover | 1 wk | Mon 7/6/09 | Fri 7/10/09 | 151 | Dawn,Henry |
153 | 100% | Make list of available utensils/pots/pans/etc/ | 2 wks | Mon 7/6/09 | Wed 7/15/09 | 151 | Dawn,Henry |
154 | 0% | Make list of Common spices/condiments/etc. | 1 wk | Mon 7/6/09 | Fri 7/10/09 | 151 | Dawn,Henry |
155 | 0% | Attain storage bins for kitchen | 1 wk | Mon 7/6/09 | Fri 7/10/09 | 151 | Dawn,Henry |
156 | 0% | Acquire tables | 1 wk | Mon 7/6/09 | Fri 7/10/09 | 151 | Dawn,Henry |
157 | 0% | Create filtration system | 4 wks | Mon 7/6/09 | Sat 7/25/09 | 151 | Dawn |
158 | 0% | Purchase propane tanks for grill | 1 day | Tue 8/18/09 | Tue 8/18/09 | 219FS-2 wks | Dale |
159 | 100% | Meal Plan | 2 wks | Mon 6/1/09 | Wed 6/10/09 | Dale | |
160 | |||||||
161 | 50% | Electrical | 102 days? | Sun 4/26/09 | Wed 8/5/09 | ||
162 | 100% | Sort extension cords to verify we have twenty-five (25) 20' | 1 day | Sun 4/26/09 | Sun 4/26/09 | Team | |
163 | 100% | Estimate camp electrical draw | 1 wk | Sun 4/26/09 | Thu 4/30/09 | Team | |
164 | 0% | Determine whether each project has electrical supply | 1 wk | Sat 8/1/09 | Wed 8/5/09 | Team | |
165 | 0% | 1 day? | Sat 8/1/09 | Sat 8/1/09 | |||
166 | 2% | Shower | 61 days | Sat 4/18/09 | Wed 6/17/09 | ||
167 | 0% | Design | 2 mons | Sat 4/18/09 | Wed 5/27/09 | 4 | Dawn,Bambi |
168 | 100% | Inspect shower tent | 1 day | Thu 5/28/09 | Thu 5/28/09 | 167 | Bambi |
169 | 0% | Build | 1 mon | Fri 5/29/09 | Wed 6/17/09 | 168 | Dawn,Bambi |
170 | |||||||
171 | 0% | Evap Pond | 89 days | Sat 4/18/09 | Wed 7/15/09 | ||
172 | 0% | Acquire Visqueen | 2 wks | Sat 4/18/09 | Mon 4/27/09 | 4 | Dawn,Bambi |
173 | 0% | Acquire lumber (5' x 10') | 2 wks | Mon 6/1/09 | Wed 6/10/09 | Dawn,Bambi | |
174 | 0% | Evaporation fountain | 7 wks | Thu 6/11/09 | Wed 7/15/09 | 173 | Dawn,Bambi |
175 | |||||||
176 | 0% | Trash Nazi | 50 days | Mon 6/1/09 | Mon 7/20/09 | ||
177 | 0% | Attain barrels | 2 mons | Mon 6/1/09 | Fri 7/10/09 | JB | |
178 | 0% | Decorate barrels | 0.5 mons | Sat 7/11/09 | Mon 7/20/09 | 177 | Bill,Henry |
179 | |||||||
180 | 100% | Sound System | 10 days | Wed 7/1/09 | Fri 7/10/09 | ||
181 | 100% | Test existing equipment | 2 wks | Wed 7/1/09 | Fri 7/10/09 | Bill | |
182 | |||||||
183 | 100% | DJ Stand (Potting Shed) | 35 days | Wed 7/1/09 | Tue 8/4/09 | ||
184 | 100% | Design | 3 wks | Wed 7/1/09 | Wed 7/15/09 | Henry,Bill | |
185 | 100% | Purchase hardware | 2 wks | Thu 7/16/09 | Sat 7/25/09 | 184 | Team |
186 | 100% | Build | 2 wks | Sun 7/26/09 | Tue 8/4/09 | 185 | Henry,Bill |
187 | |||||||
188 | 100% | Bar | 3 days | Sat 8/1/09 | Mon 8/3/09 | ||
189 | 100% | Design | 1 day | Sat 8/1/09 | Sat 8/1/09 | Alex | |
190 | 100% | Purchase hardware | 1 day | Sun 8/2/09 | Sun 8/2/09 | 189 | Alex |
191 | 100% | Build | 1 day | Mon 8/3/09 | Mon 8/3/09 | 190 | Alex |
192 | |||||||
193 | 56% | DeBOSCHery in the Garden of DeLights | 20 days | Sat 4/18/09 | Thu 5/7/09 | ||
194 | 100% | Determine name | 2 wks | Sat 4/18/09 | Mon 4/27/09 | 4 | Team |
195 | 100% | What-Where-When Listing | 1 wk | Tue 4/28/09 | Sat 5/2/09 | 194 | Dale |
196 | 100% | DJ line-up | 2 wks | Tue 4/28/09 | Thu 5/7/09 | 194 | Henry |
197 | 0% | Alcohol | 2 wks | Tue 4/28/09 | Thu 5/7/09 | 194 | Team |
198 | 0% | Bartender Lineup | 2 wks | Tue 4/28/09 | Thu 5/7/09 | 194 | Team |
199 | |||||||
200 | 0% | Develop individual task lists for teams | 1 day | Sat 8/15/09 | Sat 8/15/09 | 219FS-13 days | Dale |
201 | |||||||
202 | 54% | WNBR & Pub Crawl | 141 days | Wed 4/1/09 | Wed 8/19/09 | ||
203 | 100% | Set Date | 0 days | Wed 4/1/09 | Wed 4/1/09 | Dale | |
204 | 100% | Design mugs | 6 wks | Wed 4/1/09 | Thu 4/30/09 | 203 | Dale |
205 | 100% | Order mugs | 2 wks | Fri 5/1/09 | Sun 5/10/09 | 204 | Dale |
206 | 100% | Publish webpage | 1 wk | Mon 6/1/09 | Fri 6/5/09 | Dale | |
207 | 100% | What-Where-When Listing | 1 day | Sat 6/6/09 | Sat 6/6/09 | 206 | Dale |
208 | 100% | Recruit Host Camps | 2 wks | Wed 4/1/09 | Fri 4/10/09 | 203 | Dale |
209 | 0% | Determine cocktails | 2 wks | Sat 4/11/09 | Mon 4/20/09 | 208 | Dale |
210 | 0% | Design fliers | 4 wks | Wed 4/1/09 | Mon 4/20/09 | 203 | Dale |
211 | 0% | Print fliers | 1 day | Tue 4/21/09 | Tue 4/21/09 | 210 | Dale |
212 | 0% | Order cards | 3 wks | Mon 6/1/09 | Mon 6/15/09 | Dale | |
213 | 0% | Purchase alcohol | 2 days | Tue 8/18/09 | Wed 8/19/09 | 219SS-2 wks | Dale |
214 | |||||||
215 | 4% | On the Playa | 142 days | Sat 4/18/09 | Sun 9/6/09 | ||
216 | 100% | Determine arrival dates | 1 day | Sat 4/18/09 | Sat 4/18/09 | 4 | |
217 | 0% | Day 1 | 0.88 days | Fri 8/28/09 | Fri 8/28/09 | ||
218 | 0% | Arrival | 0.25 days | Fri 8/28/09 | Fri 8/28/09 | Team | |
219 | 0% | Arrive on playa | 0 hrs | Fri 8/28/09 | Fri 8/28/09 | ||
220 | 0% | Establish camp perimeter | 0 hrs | Fri 8/28/09 | Fri 8/28/09 | 219 | Team |
221 | 0% | Position truck and RVs | 0 hrs | Fri 8/28/09 | Fri 8/28/09 | 220 | Team |
222 | 0% | Mark off personal tent space | 0 hrs | Fri 8/28/09 | Fri 8/28/09 | 221 | Team |
223 | 0% | Mark locations for major structures | 2 hrs | Fri 8/28/09 | Fri 8/28/09 | 222 | Team |
224 | 0% | Unload | 0.38 days | Fri 8/28/09 | Fri 8/28/09 | ||
225 | 0% | Unload truck and RVs | 2 hrs | Fri 8/28/09 | Fri 8/28/09 | 222 | Team |
226 | 0% | Distribute personal items from truck and RVs | 1 hr | Fri 8/28/09 | Fri 8/28/09 | 225 | Team |
227 | 0% | Initial Setup | 0.5 days | Fri 8/28/09 | Fri 8/28/09 | ||
228 | 0% | Build essential personal living spaces (decorate later) | 2 hrs | Fri 8/28/09 | Fri 8/28/09 | 226 | Team |
229 | 0% | Mark for trenching | 2 hrs | Fri 8/28/09 | Fri 8/28/09 | 223,228 | |
230 | 0% | Construction | 0.63 days | Fri 8/28/09 | Fri 8/28/09 | ||
231 | 0% | Drill 20 octoroom holes | 1 hr | Fri 8/28/09 | Fri 8/28/09 | 223,225 | Team |
232 | 0% | Erect Octorooms | 4 hrs | Fri 8/28/09 | Fri 8/28/09 | 231 | Team |
233 | 0% | Day 2 | 3 days | Sat 8/29/09 | Mon 8/31/09 | ||
234 | 0% | Install flower gardens | 24 hrs | Sat 8/29/09 | Mon 8/31/09 | 219FS+1 day | |
235 | 0% | Trench and lay extension cords | 5 hrs | Sat 8/29/09 | Sat 8/29/09 | 219FS+1 day | |
236 | 0% | Decorate octorooms | 4 hrs | Sat 8/29/09 | Sat 8/29/09 | 232SS+1 day | |
237 | 0% | Set up sound system | 2 hrs | Sat 8/29/09 | Sat 8/29/09 | 235 | |
238 | 0% | Fencing and fence lighting | 3 hrs | Sat 8/29/09 | Sat 8/29/09 | 235 | |
239 | 0% | Kitchen shade structure | 1 hr | Sat 8/29/09 | Sat 8/29/09 | 235 | |
240 | 0% | Install shade panels in front of kitchen | 2 hrs | Sat 8/29/09 | Sat 8/29/09 | 239 | |
241 | 0% | Build shower | 1 hr | Sat 8/29/09 | Sat 8/29/09 | 237 | |
242 | 0% | Install evap pond | 1 hr | Sat 8/29/09 | Sat 8/29/09 | 237 | |
243 | 0% | Decorate personal living spaces | 4 hrs | Sat 8/29/09 | Sat 8/29/09 | 218FS+1 day | |
244 | 0% | Day 3 | 0.38 days | Sun 8/30/09 | Sun 8/30/09 | ||
245 | 0% | Install RV/truck covers | 3 hrs | Sun 8/30/09 | Sun 8/30/09 | 219FS+2 days | |
246 | 0% | Drill banner/flag holes | 2 hrs | Sun 8/30/09 | Sun 8/30/09 | 219FS+2 days | |
247 | 0% | Install banners/flags | 1 hr | Sun 8/30/09 | Sun 8/30/09 | 246 | |
248 | 0% | Schedule Johnny-on-the-Spot | 4 days | Fri 8/28/09 | Tue 9/1/09 | 218 | |
249 | |||||||
250 | 0% | Meals | 10 days | Fri 8/28/09 | Sun 9/6/09 | ||
251 | 0% | First Friday | 0.5 days | Fri 8/28/09 | Fri 8/28/09 | Bill,Dawn | |
252 | 0% | First Saturday | 1 day | Sat 8/29/09 | Sat 8/29/09 | Bambi | |
253 | 0% | First Sunday | 1 day | Sun 8/30/09 | Sun 8/30/09 | Ryan | |
254 | 0% | Monday | 1 day | Mon 8/31/09 | Mon 8/31/09 | Dale | |
255 | 0% | Tuesday | 1 day | Tue 9/1/09 | Tue 9/1/09 | Henry | |
256 | 0% | Wednesday | 1 day | Wed 9/2/09 | Wed 9/2/09 | Monetta | |
257 | 0% | Thursday | 1 day | Thu 9/3/09 | Thu 9/3/09 | Gary | |
258 | 0% | Friday | 1 day | Fri 9/4/09 | Fri 9/4/09 | Alex | |
259 | 0% | Second Saturday | 1 day | Sat 9/5/09 | Sat 9/5/09 | JB | |
260 | 0% | Second Sunday (Leftovers) | 1 day | Sun 9/6/09 | Sun 9/6/09 | Shanan | |
261 | |||||||
262 | 0% | DeBoschery in the Garden of DeLights | 0.5 days | Tue 9/1/09 | Tue 9/1/09 | ||
263 | 0% | Bartenders | 0.5 days | Tue 9/1/09 | Tue 9/1/09 | ||
264 | 0% | 8:00 - 9:00 | 1 hr | Tue 9/1/09 | Tue 9/1/09 | ||
265 | 0% | 9:00 - 10:00 | 1 hr | Tue 9/1/09 | Tue 9/1/09 | Dave Chesavage,Dale | |
266 | 0% | 10:00 - 11:00 | 1 hr | Tue 9/1/09 | Tue 9/1/09 | ||
267 | 0% | 11:00 - 12:00 | 1 hr | Tue 9/1/09 | Tue 9/1/09 | ||
268 | 0% | Bar Back | 4 hrs | Tue 9/1/09 | Tue 9/1/09 | ||
269 | 0% | DJs | 0.25 days | Tue 9/1/09 | Tue 9/1/09 | ||
270 | 0% | 8:00 - 10:00 | 2 hrs | Tue 9/1/09 | Tue 9/1/09 | Ryan | |
271 | 0% | 10:00 - 12:00 | 2 hrs | Tue 9/1/09 | Tue 9/1/09 | Henry | |
272 | |||||||
273 | 0% | WNBR & Pub Crawl | 0.13 days | Wed 9/2/09 | Wed 9/2/09 | ||
274 | 0% | Bartenders | 1 hr | Wed 9/2/09 | Wed 9/2/09 | ||
275 | 0% | DJ | 1 hr | Wed 9/2/09 | Wed 9/2/09 | ||
276 | |||||||
277 | 0% | High Tea | 0.25 days | Thu 9/3/09 | Thu 9/3/09 | ||
278 | 0% | Brewmeisters | 2 hrs | Thu 9/3/09 | Thu 9/3/09 | ||
279 | 0% | DJ | 2 hrs | Thu 9/3/09 | Thu 9/3/09 | Minimonk |